Wednesday, April 28, 2010

Week Four: Wednesday, 28th of April, 2010

I joined Mr. Mohsin to site SSU Google CJ9. The project involves a construction of 33KV manhole.
I had learned about the reinforcement installation and how they place the steel bars in positions by tie them using small steel fibers.