Week Five: Tuesday, 4th of May, 2010

Today was a the hardest day for me since i started my training program because i have visited four different sites.
In the morning, I joined Mr. Kamal to the following sites:
1.18-R5, Putra Jaya (involve installation of 13 manholes)
2.17. RK3, Putra Jaya (involve installation of 7 manholes)
3.International school site, Flagship Zone, Cyber Jaya (involve installation of 2 manholes)
The visits is done daily to check the work process and to make sure that the project is in schedule.
In the afternoon, Mr. Mohsin asked me to go with him to Cyber Jaya Park site, as there was a rodding test conducted between two manholes.
I learned about the procedure of the rodding test as I watched closely the process by entering the manhole.

18-R5, Putra Jaya site:


17. RK3, Putra Jaya site:




International school site:



Cyber Jaya Park site: